4100 yard pour
| Beast | 05-02-2012 | comment profile send pm notify |
|
started a 4100 yard pour friday night at 7 pm and finished at 1 pm saturday, pump place and finish |
||
| Beast | 05-02-2012 | reply profile send pm notify |
|
equipment performed flawlessly,men did great,angelle concrete averaged 240+ per hour, awesome job. |
||
| Dont need one | 05-02-2012 | reply profile send pm notify |
|
Nice job, was that a refinery. |
||
| Dont need one | 05-02-2012 | reply profile send pm notify |
|
Who pays for the huge cribbing mats you set the pump on. |
||
| Beast | 05-03-2012 | reply profile send pm notify |
|
cant say where it was, its a chemiical plant, and the contractor supplied the matts |
||
| gillrod1 | 05-03-2012 | reply profile send pm notify |
|
is that TMI pumps on that job |
||
| Beast | 05-04-2012 | reply profile send pm notify |
|
yep
|
||